Veseta Litovel, phase 3

The third phase in the construction of a production plant for this leading soft-drink producer in Litovel

Veseta Litovel, phase 3

Veseta Litovel, phase 3

  • Zadavatel: Veseta Litovel
  • Datum realizace: August-November 2009

In mid August 2009, we launched the third phase in the development of the production plant for Veseta Litovel; the skeleton assembly began in early September. This is a five-bay warehouse hall, connected to the existing hall constructed in 2006 and 2007. The hall has dimensions of 90×107.6 metres, formed by 90 types of elements. The girder span is 18 metres, and the height up to the girders is 13.8 metres.
The envelope is formed by PUR panels, from a height of 4.5 metres up to the gable. The roof is formed with welded metal sheets. The hall consists of seven ramp bridges. The delivery of the skeleton and the envelope will be completed in mid November 2009.

Other pictures

  • Reinforcement cage for the piles Reinforcement cage for the piles
  • Course of pile construction Course of pile construction
  • Foundation pockets Foundation pockets
  • Commencement of assembly Commencement of assembly
  • Assembly work in progress Assembly work in progress
  • Joint detail Joint detail
  • View of the hall View of the hall
  • Loading ramp bridge - course of concrete work Loading ramp bridge - course of concrete work
  • Warehouse building Warehouse building
  • Connection to the existing building Connection to the existing building
  • Loading ramp bridge Loading ramp bridge
  • Roof Roof
  • Wall with loading ramp bridges Wall with loading ramp bridges
  • Roof structure Roof structure
  • Pillars Pillars